Context
Development of environmental licensing, monitoring and various services for the gold mine, access road and transmission line in the Amazon biome, in the state of Pará, Brazil.
Methodology performed
For the development of services, the Clam team provided, among others, the following services: characterization and qualitative and quantitative hydrogeological/hydrological monitoring, background hydrogeochemical characterization, characterization of acid drainage generation potential, water studies to define water balance and pit dewatering, technical studies for water use permits and effluent discharge permits, development of the Environmental Management System to be used during mine operation, as well as fauna and flora monitoring and environmental licensing for the landfill and concrete plant that will serve the project.
Results
Meeting the various environmental demands of the customer with efficiency and assertiveness.
Status
Complete
Year
2019
Category
Environment